Skip to content

FP7

SAFERAIL

Development of Novel Inspection Systems for Railway Wheelsets

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 4,448,701
EU contribution
EUR 3,000,000
Participants
11 from 6 countries
Topic
FP7_SST-2007-4.1-01
Grant agreement
218674

Coordinated by Twi Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Twi LimitedGBUnited KingdomCoordinatorEUR 675,000known name (0.95)
Alfa Products and TechnologiesBEBelgiumParticipantEUR 392,618PIC (1.00)
Vlaamse Vervoersmaatschappij De LijnBEBelgiumParticipantEUR 139,300PIC (1.00)
Feldman Enterprises LimitedCYCyprusParticipantEUR 169,150PIC (1.00)
Societe Nationale SncfFRFranceParticipantEUR 107,500known name (0.95)
Technical Software Consultants LtdGBUnited KingdomParticipantEUR 253,750PIC (1.00)
The University of BirminghamGBUnited KingdomParticipantEUR 402,500known name (0.95)
VTG Rail UK LtdGBUnited KingdomParticipantEUR 83,500PIC (1.00)
Mistras Group Hellas Anonymos Biomichaniki Kai Emporiki EtaireiaGRGreeceParticipantEUR 278,300PIC (1.00)
EMEF, SA - Empresa de Manutenção de Equipamento Ferroviário, SAPTPortugalParticipantEUR 113,500PIC (1.00)
Instituto de Soldadura e QualidadePTPortugalParticipantEUR 384,882PIC (1.00)

Changes of the consortium

First seen on with 11 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.