RIVAS

Railway Induced Vibration Abatement Solutions

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 8,163,798
EU contribution
EUR 5,199,995
Participants
26 from 8 countries
Topic
FP7_SST.2010.1.1-3.
Grant agreement
265754

Coordinated by Union Internationale des Chemins de Fer (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Union Internationale des Chemins de FerFRFranceCoordinatorEUR 281,000PIC (1.00)
Dynamics,structures and Systems International NVBEBelgiumParticipantEUR 229,336PIC (1.00)
Katholieke Universiteit LeuvenBEBelgiumParticipantEUR 322,980PIC (1.00)
Union des Industries Ferroviaires Europeennes - UnifeBEBelgiumParticipantEUR 116,200PIC (1.00)
Prose AGCHSwitzerlandParticipantEUR 80,000PIC (1.00)
Schweizerische Bundesbahnen SbbCHSwitzerlandParticipantEUR 395,250known name (0.95)
Bundesanstalt Fuer Materialforschung und -PruefungDEGermanyParticipantEUR 314,818PIC (1.00)
Deutsche Bahn AGDEGermanyParticipantEUR 324,091known name (0.97)
Eiffage Rail GmbHDEGermanyParticipantEUR 139,788PIC (1.00)
Keller Holding GmbHDEGermanyParticipantEUR 187,025PIC (1.00)
Rail.one GmbHDEGermanyParticipantEUR 170,231PIC (1.00)
Tuv Rheinland Forschungs- und Innovations Management GmbHDEGermanyParticipantEUR 305,149PIC (1.00)
Administrador de Infraestructuras FerroviariasESSpainParticipantEUR 102,617known name (0.95)
Centro de Estudios y Experimentacion de Obras PublicasESSpainParticipantEUR 181,800VAT number (0.97)
Alstom Transport SAFRFranceParticipantEUR 141,147PIC (1.00)
Centre Scientifique et Technique du BatimentFRFranceParticipantEUR 129,412PIC (1.00)
Regie Autonome des Transports ParisiensFRFranceParticipantEUR 32,094known name (0.95)
Sateba Systeme Vagneux SAFRFranceParticipantEUR 44,450PIC (1.00)
Societe Nationale SncfFRFranceParticipantEUR 256,766known name (0.95)
VibratecFRFranceParticipantEUR 386,909PIC (1.00)
Pandrol LimitedGBUnited KingdomParticipantEUR 67,381PIC (1.00)
University of SouthamptonGBUnited KingdomParticipantEUR 210,784known name (0.95)
Lucchini Rs SpAITItalyParticipantEUR 62,006PIC (1.00)
Alstom Rail Sweden ABSESwedenParticipantEUR 257,738PIC (1.00)
Chalmers Tekniska Hogskola ABSESwedenParticipantEUR 224,976PIC (1.00)
Name not shownNot statedParticipantNot statedPIC (1.00)

Changes of the consortium

First seen on with 26 participants from 9 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.