HORIZON
iAMP-Hydro
intelligent Asset Management Platform for Hydropower operation and maintenance
- Programme
- Horizon Europe
- Started
- Ends
- Duration
- 36 months
- Total cost
- Not stated
- EU contribution
- EUR 4,151,084
- Participants
- 9 from 6 countries
- Topic
- HORIZON_HORIZON-CL5-2022-D3-03-08
- Grant agreement
- 101122167
Coordinated by The Provost, Fellows, Foundation Scholars & the Other Members of Board, of the College of the Holy & Undivided Trinity of Queen Elizabeth Near Dublin (IEIreland).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| The Provost, Fellows, Foundation Scholars & the Other Members of Board, of the College of the Holy & Undivided Trinity of Queen Elizabeth Near Dublin | IEIreland | Coordinator | EUR 696,159 | PIC (1.00) |
| Wirtschaft und Infrastruktur GmbH & Co Planungs KG | DEGermany | Participant | EUR 261,500 | PIC (1.00) |
| Cuerva Energia Slu | ESSpain | Participant | EUR 393,125 | PIC (1.00) |
| Fundacion Cartif | ESSpain | Participant | EUR 371,250 | PIC (1.00) |
| Anonimi Etairia Diaxeirisis Ananeosimon Pigon Energeias | GRGreece | Participant | EUR 445,938 | PIC (1.00) |
| Dimosia Epicheirisi Ilektrismou Anonymi Etaireia | GRGreece | Participant | EUR 272,500 | PIC (1.00) |
| Easy Hydro Limited | IEIreland | Participant | EUR 456,325 | PIC (1.00) |
| Norce Norwegian Research Centre As | NONorway | Participant | EUR 370,663 | known name (0.95) |
| Universitatea Nationala de Stiintasi Tehnologie Politehnica Bucuresti | RORomania | Participant | EUR 290,500 | PIC (1.00) |
Changes of the consortium
First seen on with 9 participants from 6 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.