Advanced Infrastructure for Knowledge Based Services for Buildings Restoring

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 2,639,582
EU contribution
EUR 1,867,100
Participants
13 from 5 countries
Topic
FP7_NMP-2007-4.0-6
Grant agreement
214567

Coordinated by Fundacion Santa Maria la Real del Patrimonio Historico (ESSpain).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Fundacion Santa Maria la Real del Patrimonio HistoricoESSpainCoordinatorEUR 107,014PIC (1.00)
Tietjen Holz-Kunststoff-Technik GmbH & Co KGDEGermanyParticipantEUR 101,100PIC (1.00)
Ventimola GmbH & Co Dammtechnik KGDEGermanyParticipantEUR 130,226PIC (1.00)
Fundacion Tecnalia Research & InnovationESSpainParticipantEUR 310,950PIC (1.00)
Tecpropasa Euskadi SAESSpainParticipantEUR 82,520PIC (1.00)
Confederation de L' Artisanat et des Petites Entreprises du BatimentFRFranceParticipantEUR 68,399PIC (1.00)
Sarl Andre CottenceauFRFranceParticipantEUR 64,800PIC (1.00)
Teicos Costruzioni SRLITItalyParticipantEUR 94,000PIC (1.00)
3M2P - Construcao e Reabilitacao de Edificios LdaPTPortugalParticipantEUR 76,500PIC (1.00)
Inesc Tec - Instituto de Engenhariade Sistemas e Computadores, Tecnologia e CienciaPTPortugalParticipantEUR 168,505PIC (1.00)
STB - Reabilitacao do Patrimonio Edificado LdaPTPortugalParticipantEUR 58,950PIC (1.00)
Universidade do PortoPTPortugalParticipantEUR 77,181known name (0.95)
Vortal-Comercio Electronico Consultadoria e Multimedia SAPTPortugalParticipantEUR 113,600PIC (1.00)

Changes of the consortium

First seen on with 13 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.