FP7
H-KNOW
Advanced Infrastructure for Knowledge Based Services for Buildings Restoring
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 36 months
- Total cost
- EUR 2,639,582
- EU contribution
- EUR 1,867,100
- Participants
- 13 from 5 countries
- Topic
- FP7_NMP-2007-4.0-6
- Grant agreement
- 214567
Coordinated by Fundacion Santa Maria la Real del Patrimonio Historico (ESSpain).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Fundacion Santa Maria la Real del Patrimonio Historico | ESSpain | Coordinator | EUR 107,014 | PIC (1.00) |
| Tietjen Holz-Kunststoff-Technik GmbH & Co KG | DEGermany | Participant | EUR 101,100 | PIC (1.00) |
| Ventimola GmbH & Co Dammtechnik KG | DEGermany | Participant | EUR 130,226 | PIC (1.00) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 310,950 | PIC (1.00) |
| Tecpropasa Euskadi SA | ESSpain | Participant | EUR 82,520 | PIC (1.00) |
| Confederation de L' Artisanat et des Petites Entreprises du Batiment | FRFrance | Participant | EUR 68,399 | PIC (1.00) |
| Sarl Andre Cottenceau | FRFrance | Participant | EUR 64,800 | PIC (1.00) |
| Teicos Costruzioni SRL | ITItaly | Participant | EUR 94,000 | PIC (1.00) |
| 3M2P - Construcao e Reabilitacao de Edificios Lda | PTPortugal | Participant | EUR 76,500 | PIC (1.00) |
| Inesc Tec - Instituto de Engenhariade Sistemas e Computadores, Tecnologia e Ciencia | PTPortugal | Participant | EUR 168,505 | PIC (1.00) |
| STB - Reabilitacao do Patrimonio Edificado Lda | PTPortugal | Participant | EUR 58,950 | PIC (1.00) |
| Universidade do Porto | PTPortugal | Participant | EUR 77,181 | known name (0.95) |
| Vortal-Comercio Electronico Consultadoria e Multimedia SA | PTPortugal | Participant | EUR 113,600 | PIC (1.00) |
Changes of the consortium
First seen on with 13 participants from 5 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.