Skip to content

FP7

MUSECORR

Protection of cultural heritage by real-time corrosion monitoring

Programme
Seventh Framework Programme
Started
Ends
Duration
38 months
Total cost
EUR 993,226
EU contribution
EUR 765,595
Participants
7 from 5 countries
Topic
FP7_ENV.2008.3.2.2.1.
Grant agreement
226539

Coordinated by Institut de la Corrosion Sasu (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Institut de la Corrosion SasuFRFranceCoordinatorEUR 201,880PIC (1.00)
Schweizerisches NationalmuseumCHSwitzerlandParticipantEUR 36,851known name (0.95)
Vysoka Skola Chemicko-Technologicka v PrazeCZCzechiaParticipantEUR 122,728known name (0.95)
Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung EvDEGermanyParticipantEUR 174,164known name (0.95)
NationalmuseetDKDenmarkParticipantEUR 36,920known name (0.95)
Centre de Recherche et de Restauration des Musees de FranceFRFranceParticipantEUR 39,600known name (0.95)
Nke SAFRFranceParticipantEUR 153,452PIC (1.00)

Changes of the consortium

First seen on with 7 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.