FP7
PRONTO
Productivity, Non-Tariff Measures and Openness
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 3,265,847
- EU contribution
- EUR 2,498,444
- Participants
- 12 from 8 countries
- Topic
- FP7_SSH.2013.4.3-3
- Grant agreement
- 613504
Coordinated by Universitaet Bern (CHSwitzerland).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Universitaet Bern | CHSwitzerland | Coordinator | EUR 609,099 | PIC (1.00) |
| Wiener Institut Fur Internationale Wirtschaftsvergleiche | ATAustria | Participant | EUR 300,018 | PIC (1.00) |
| Ecole D'Economie de Paris | FRFrance | Participant | EUR 226,136 | PIC (1.00) |
| London School of Economics and Political Science | GBUnited Kingdom | Participant | EUR 199,678 | PIC (1.00) |
| The Centre for Economic Policy Research | GBUnited Kingdom | Participant | EUR 172,650 | PIC (1.00) |
| The University of Sussex | GBUnited Kingdom | Participant | EUR 55,832 | known name (0.95) |
| University of Surrey | GBUnited Kingdom | Participant | EUR 34,648 | known name (0.95) |
| Athens University of Economics and Business - Research Center | GRGreece | Participant | EUR 93,440 | PIC (1.00) |
| University College Dublin, National University of Ireland, Dublin | IEIreland | Participant | EUR 383,672 | VAT number (0.97) |
| Centro Studi Luca D'Agliano Ets | ITItaly | Participant | EUR 147,248 | PIC (1.00) |
| Ecorys Nederland BV | NLNetherlands | Participant | EUR 132,304 | PIC (1.00) |
| Stichting Wageningen Research | NLNetherlands | Participant | EUR 143,720 | known name (0.95) |
Changes of the consortium
First seen on with 12 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.