FP7
TOWERPOWER
Continuous monitoring of the structural condition of the tower and supporting structure of floating and static offshore wind turbines
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 44 months
- Total cost
- EUR 2,065,478
- EU contribution
- EUR 1,469,000
- Participants
- 15 from 8 countries
- Topic
- FP7_SME-2013-2
- Grant agreement
- 605013
Coordinated by Capenergies Association (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Capenergies Association | FRFrance | Coordinator | EUR 280,035 | PIC (1.00) |
| Wlb Limited | CYCyprus | Participant | EUR 30,451 | PIC (1.00) |
| Aalborg Kommune | DKDenmark | Participant | EUR 1,867 | known name (0.95) |
| Asociacion Empresarial Eolica | ESSpain | Participant | EUR 362,551 | PIC (1.00) |
| Cluster de Energias Renovables y Soluciones Energeticas en Castilla y Leon | ESSpain | Participant | EUR 108,757 | PIC (1.00) |
| Tecopy SA | ESSpain | Participant | EUR 17,239 | PIC (1.00) |
| Centre Technique des Industries Mecaniques | FRFrance | Participant | EUR 62,527 | PIC (1.00) |
| Kingston Computer Consultancy Limited | GBUnited Kingdom | Participant | EUR 37,580 | PIC (1.00) |
| Moniteye Ltd | GBUnited Kingdom | Participant | EUR 42,631 | PIC (1.00) |
| Smithers Purslow Property Services Ltd | GBUnited Kingdom | Participant | Not stated | PIC (1.00) |
| Twi Limited | GBUnited Kingdom | Participant | EUR 72,017 | known name (0.95) |
| Iknowhow SA | GRGreece | Participant | Not stated | PIC (1.00) |
| Innora Proigmena Technologika Systimata Kai Ypiresies Ae | GRGreece | Participant | EUR 39,602 | PIC (1.00) |
| Associazione Italiana Prove Non Distruttive | ITItaly | Participant | EUR 353,855 | PIC (1.00) |
| Teknisk Data As | NONorway | Participant | EUR 22,086 | PIC (1.00) |
Changes of the consortium
First seen on with 15 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.