FP7
AMBASSADOR
Autonomous Management System Developed for Building and District Levels
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 9,619,374
- EU contribution
- EUR 6,499,513
- Participants
- 14 from 11 countries
- Topic
- FP7_EeB.NMP.2012-1
- Grant agreement
- 314175
Coordinated by Schneider Electric Industries Sas (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Schneider Electric Industries Sas | FRFrance | Coordinator | EUR 1,016,337 | PIC (1.00) |
| European Consulting Brussels | BEBelgium | Participant | EUR 114,480 | PIC (1.00) |
| Csem Centre Suisse D'Electronique et de Microtechnique SA - Recherche et Developpement | CHSwitzerland | Participant | EUR 1,075,607 | PIC (1.00) |
| Neurobat AG | CHSwitzerland | Participant | EUR 285,200 | PIC (1.00) |
| Planair SA | CHSwitzerland | Participant | EUR 314,813 | known name (0.95) |
| Amires Sro | CZCzechia | Participant | EUR 222,600 | PIC (1.00) |
| Leclanche GmbH | DEGermany | Participant | EUR 220,542 | PIC (1.00) |
| Zigor Research & Development Aie | ESSpain | Participant | EUR 253,200 | PIC (1.00) |
| Teknologian Tutkimuskeskus Vtt OY | FIFinland | Participant | Not stated | known name (0.95) |
| Cisco Systems Ltd | GBUnited Kingdom | Participant | Not stated | PIC (1.00) |
| Zedfactory Europe Limited | GBUnited Kingdom | Participant | EUR 168,900 | PIC (1.00) |
| Ethnicon Metsovion Polytechnion | GRGreece | Participant | EUR 467,680 | PIC (1.00) |
| Rina Consulting SpA | ITItaly | Participant | EUR 377,727 | PIC (1.00) |
| Cisco Systems International BV | NLNetherlands | Participant | EUR 122,906 | PIC (1.00) |
Changes of the consortium
First seen on with 14 participants from 11 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.