HORIZON
DRASTIC
Demonstrating Real and Affordable Sustainable Building Solutions with Top-level whole life-cycle performance and Improved Circularity
- Programme
- Horizon Europe
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 7,854,998
- EU contribution
- EUR 5,957,809
- Participants
- 23 from 8 countries
- Topic
- HORIZON_HORIZON-CL5-2022-D4-02-05
- Grant agreement
- 101123330
Coordinated by Vlaamse Instelling Voor Technologisch Onderzoek N.V. (BEBelgium).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Vlaamse Instelling Voor Technologisch Onderzoek N.V. | BEBelgium | Coordinator | EUR 1,158,741 | PIC (1.00) |
| Worldgbc Europe | BEBelgium | Participant | EUR 446,940 | PIC (1.00) |
| Caala GmbH | DEGermany | Participant | EUR 280,125 | PIC (1.00) |
| Saint-Gobain Isover G+h AG | DEGermany | Third party | Not stated | PIC (1.00) |
| Saint-Gobain Weber GmbH | DEGermany | Participant | EUR 371,134 | PIC (1.00) |
| Tallinna Tehnikaülikool | EEEstonia | Participant | EUR 357,563 | known name (0.95) |
| Timbeco Ehitus Ou | EEEstonia | Participant | EUR 391,116 | PIC (1.00) |
| Acsa Obras e Infraestructuras Sau | ESSpain | Participant | EUR 92,123 | PIC (1.00) |
| Adec Global SL | ESSpain | Participant | EUR 51,488 | PIC (1.00) |
| Celsa Opco, SA | ESSpain | Participant | EUR 129,150 | PIC (1.00) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 373,938 | PIC (1.00) |
| Lezama Demoliciones SL | ESSpain | Participant | EUR 139,725 | PIC (1.00) |
| Universitat Politecnica de Catalunya | ESSpain | Participant | EUR 205,813 | known name (0.97) |
| Association Hqe | FRFrance | Third party | Not stated | PIC (1.00) |
| Coramine | FRFrance | Third party | Not stated | PIC (1.00) |
| Icade | FRFrance | Associated partner | EUR 0 | PIC (1.00) |
| Saint Gobain Recherche SA | FRFrance | Participant | EUR 758,524 | PIC (1.00) |
| Saint-Gobain Solutions France | FRFrance | Third party | Not stated | PIC (1.00) |
| Madaster Shared Services BV | NLNetherlands | Participant | EUR 211,088 | PIC (1.00) |
| Universiteit Maastricht | NLNetherlands | Participant | EUR 569,032 | known name (0.95) |
| Omtre As | NONorway | Participant | EUR 213,938 | PIC (1.00) |
| Productif Norway As | NONorway | Participant | EUR 207,375 | PIC (1.00) |
| Saint-Gobain Ecophon Aktiebolag | SESweden | Third party | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 23 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.