IASIS

Intelligent Adaptable Surface with Optical Fiber Sensing for Pressure-Tension Relief

Programme
Seventh Framework Programme
Started
Ends
Duration
26 months
Total cost
EUR 1,495,000
EU contribution
EUR 1,115,000
Participants
9 from 4 countries
Grant agreement
232479

Coordinated by S.S.F. Safe Smart Fabric Adaptable Surface Ltd (CYCyprus).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
S.S.F. Safe Smart Fabric Adaptable Surface LtdCYCyprusCoordinatorEUR 352,500PIC (1.00)
Nicosia General HospitalCYCyprusParticipantEUR 55,000PIC (1.00)
Medcom Gesellschaft Fuer Medizinische Bildverarbeitung MbhDEGermanyParticipantEUR 215,000PIC (1.00)
Fujikura Europe LtdGBUnited KingdomParticipantEUR 10,000PIC (1.00)
Aristotelio Panepistimio ThessalonikisGRGreeceParticipantEUR 10,000PIC (1.00)
Bioimerosin Laboratories S.A.GRGreeceParticipantEUR 260,000PIC (1.00)
Comitech S.A.GRGreeceParticipantEUR 147,500PIC (1.00)
Filoktitis - Center for Rehabilitation, Reintegration and Care of the Elderly, Handicapped and Sick Persons S.AGRGreeceParticipantEUR 55,000PIC (1.00)
Idryma Technologias Kai ErevnasGRGreeceParticipantEUR 10,000PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 4 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.