Skip to content

H2020

MOSAR

MOdular Spacecraft Assembly and Reconfiguration

Programme
Horizon 2020
Started
Ends
Duration
28 months
Total cost
EUR 3,999,962
EU contribution
EUR 3,999,962
Participants
9 from 6 countries
Topic
H2020_SPACE-12-TEC-2018
Grant agreement
821996

Coordinated by Space Applications Services NV (BEBelgium).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Space Applications Services NVBEBelgiumCoordinatorEUR 1,388,183PIC (1.00)
Deutsches Zentrum Fur Luft - Und Raumfahrt EvDEGermanyParticipantEUR 626,795known name (0.97)
Gmv Aerospace and Defence S.A.ESSpainParticipantEUR 464,875known name (0.95)
Mag Soar S.L.ESSpainParticipantEUR 235,625PIC (1.00)
Ellidiss TechnologiesFRFranceParticipantEUR 169,500PIC (1.00)
Thales Alenia Space FranceFRFranceParticipantEUR 161,625known name (0.95)
Thales Alenia Space UK LtdGBUnited KingdomParticipantEUR 392,091PIC (1.00)
University of StrathclydeGBUnited KingdomParticipantEUR 171,269known name (0.95)
Sitael SpAITItalyParticipantEUR 390,000PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.