H2020
ERIFORE
Research Infrastructure for Circular Forest Bioeconomy
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 25 months
- Total cost
- EUR 2,630,950
- EU contribution
- EUR 2,628,700
- Participants
- 15 from 10 countries
- Topic
- H2020_INFRADEV-1-2014
- Grant agreement
- 654371
Coordinated by Teknologian Tutkimuskeskus Vtt OY (FIFinland).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Teknologian Tutkimuskeskus Vtt OY | FIFinland | Coordinator | EUR 417,304 | known name (0.95) |
| Kompetenzzentrum Holz GmbH | ATAustria | Participant | EUR 162,500 | known name (0.95) |
| Bio Base Europe Pilot Plant Vzw | BEBelgium | Participant | EUR 115,000 | known name (0.95) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | EUR 290,273 | known name (0.95) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 182,500 | PIC (1.00) |
| Aalto Korkeakoulusaatio Sr | FIFinland | Participant | EUR 210,000 | VAT number (0.97) |
| Institut National de Recherche Pour L'Agriculture, L'Alimentation et L'Environnement | FRFrance | Participant | EUR 102,844 | known name (0.95) |
| Institut Technologique Fcba (Foretcellulose Bois-Construction Ameublement) | FRFrance | Participant | EUR 168,364 | VAT number (0.97) |
| Latvijas Valsts Koksnes Kimijas Instituts | LVLatvia | Participant | EUR 230,000 | known name (0.95) |
| Sintef As | NONorway | Participant | EUR 147,486 | known name (0.95) |
| Stiftelsen Sintef | NONorway | Participant | EUR 74,889 | PIC (1.00) |
| Institutul de Chimie Macromoleculara Petru Poni | RORomania | Participant | EUR 100,000 | known name (0.95) |
| Kungliga Tekniska Hoegskolan | SESweden | Participant | EUR 117,000 | PIC (1.00) |
| Rise Processum AB | SESweden | Participant | EUR 310,540 | PIC (1.00) |
| Rise Research Institutes of Sweden AB | SESweden | Third party | Not stated | known name (0.95) |
Changes of the consortium
First seen on with 15 participants from 10 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.