Skip to content

FP7

Riblet

The Development and Construction of a Master Mould for Riblet Construction

Programme
Seventh Framework Programme
Started
Ends
Duration
31 months
Total cost
EUR 349,992
EU contribution
EUR 262,494
Participants
5 from 4 countries
Topic
FP7_JTI-CS-2012-2-SFWA-01-050
Grant agreement
325919

Coordinated by Axess Technologies Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Axess Technologies LimitedGBUnited KingdomCoordinatorEUR 29,250PIC (1.00)
3D AGCHSwitzerlandParticipantEUR 33,750PIC (1.00)
Crealas GmbHCHSwitzerlandParticipantEUR 90,000PIC (1.00)
Machovia Technology Innovations GmbHDEGermanyParticipantEUR 76,500PIC (1.00)
Mk Fluidics OYFIFinlandParticipantEUR 32,994PIC (1.00)

Changes of the consortium

First seen on with 5 participants from 4 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.