FP7

PLACYD

Pilot Line For Self Assembly Copolymer Delivery

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 14,929,925
EU contribution
EUR 2,239,489
Participants
9 from 5 countries
Topic
FP7_SP1-JTI-ENIAC-2013-2-7
Grant agreement
621277

Coordinated by Arkema France SA (FRFrance).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Arkema France SAFRFranceCoordinatorEUR 763,002PIC (1.00)
Agencia Estatal Consejo Superior de Investigaciones CientificasESSpainParticipantEUR 34,465PIC (1.00)
Centre National de la Recherche Scientifique CnrsFRFranceParticipantEUR 96,819known name (0.95)
Mentor Graphics Development Crolles SarlFRFranceParticipantEUR 124,199PIC (1.00)
Stmicroelectronics Crolles 2 SasFRFranceParticipantEUR 66,944PIC (1.00)
Intel Research and Innovation Ireland LimitedIEIrelandParticipantEUR 26,962PIC (1.00)
University College Cork - National University of Ireland, CorkIEIrelandParticipantEUR 43,875VAT number (0.97)
Applied Materials Israel LtdILIsraelParticipantEUR 549,000PIC (1.00)
Asml Netherlands B.V.NLNetherlandsParticipantEUR 94,500PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.