Skip to content

H2020

IN2TRACK

Research into enhanced tracks, switches and structures

Programme
Horizon 2020
Started
Ends
Duration
32 months
Total cost
EUR 2,799,993
EU contribution
EUR 2,799,993
Participants
31 from 10 countries
Topic
H2020_S2R-CFM-IP3-01-2016
Grant agreement
730841

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
AC2T Research GmbHATAustriaParticipantEUR 72,945known name (0.95)
Getzner Werkstoffe GmbHATAustriaParticipantEUR 16,733PIC (1.00)
Kirchdorfer Fertigteilholding GmbHATAustriaParticipantEUR 16,850PIC (1.00)
Materials Center Leoben Forschung GmbHATAustriaParticipantEUR 28,109known name (0.95)
OBB-Infrastruktur AGATAustriaParticipantEUR 66,658known name (0.95)
Plasser & Theurer Export von Bahnbaumaschinen Gesellschaft MbhATAustriaParticipantEUR 43,460PIC (1.00)
Virtual Vehicle Research GmbHATAustriaParticipantEUR 64,344PIC (1.00)
Voestalpine Rail Technology GmbHATAustriaParticipantEUR 58,670PIC (1.00)
Voestalpine Railway Systems GmbHATAustriaParticipantEUR 33,533PIC (1.00)
Wiener Linien GmbH &Co KGATAustriaParticipantEUR 20,877PIC (1.00)
Bls AGCHSwitzerlandParticipantEUR 0known name (0.95)
Schweizerische Bundesbahnen SbbCHSwitzerlandParticipantEUR 0known name (0.95)
Acciona Construccion SAESSpainParticipantEUR 168,873PIC (1.00)
Centro de Estudios de Materiales y Control de Obra SAESSpainParticipantEUR 31,108PIC (1.00)
Universidad del Pais Vasco/ Euskal Herriko UnibertsitateaESSpainParticipantEUR 17,776known name (0.95)
VaylavirastoFIFinlandParticipantEUR 47,614known name (0.95)
RaileniumFRFranceParticipantEUR 93,949PIC (1.00)
Saarstahl Rail SasFRFranceParticipantEUR 35,553PIC (1.00)
Sncf ReseauFRFranceParticipantEUR 213,313known name (0.95)
Vossloh CogiferFRFranceParticipantEUR 53,328PIC (1.00)
Cranfield UniversityGBUnited KingdomThird partyNot statedknown name (0.95)
Network Rail Infrastructure LimitedGBUnited KingdomParticipantEUR 719,206known name (0.95)
The University of BirminghamGBUnited KingdomThird partyNot statedknown name (0.95)
The University of SheffieldGBUnited KingdomThird partyNot statedknown name (0.95)
University of HuddersfieldGBUnited KingdomThird partyNot statedknown name (0.95)
University of SouthamptonGBUnited KingdomThird partyNot statedknown name (0.95)
Infraestruturas de Portugal SAPTPortugalParticipantEUR 38,090known name (0.95)
Chalmers Tekniska Hogskola ABSESwedenThird partyNot statedPIC (1.00)
Lulea Tekniska UniversitetSESwedenThird partyNot statedknown name (0.95)
Slovenske Zeleznice DooSISloveniaParticipantEUR 50,788PIC (1.00)
Turkiye Cumhuriyeti Devlet Demir Yollari Isletmesi Genel MudurluguTRTürkiyeParticipantEUR 63,486PIC (1.00)

Changes of the consortium

First seen on with 31 participants from 10 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.