FP7

OPTO-CLAVE

Design, implementation and validation of an automatic learning cure cycle optimisation process for the eco-efficient autoclave processing of composite materials

Programme
Seventh Framework Programme
Started
Ends
Duration
15 months
Total cost
EUR 99,707
EU contribution
EUR 74,780
Participants
2 from 2 countries
Topic
FP7_JTI-CS-2012-1-ECO-01-041
Grant agreement
323520

Coordinated by Twi Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Twi LimitedGBUnited KingdomCoordinatorEUR 38,137known name (0.95)
Advances & Innovation in Science & Engineering Co EeGRGreeceParticipantEUR 36,643PIC (1.00)

Changes of the consortium

First seen on with 2 participants from 2 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.