FP7
GOALDS
GOAL Based Damage Stability
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 38 months
- Total cost
- EUR 4,644,685
- EU contribution
- EUR 2,951,883
- Participants
- 19 from 9 countries
- Topic
- FP7_SST.2008.4.1.1.
- Grant agreement
- 233876
Coordinated by Ethnicon Metsovion Polytechnion (GRGreece).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Ethnicon Metsovion Polytechnion | GRGreece | Coordinator | EUR 523,400 | PIC (1.00) |
| Schiffbautechnische Versuchsanstalt in Wien GmbH | ATAustria | Participant | EUR 249,600 | PIC (1.00) |
| Dnv Se | DEGermany | Participant | Not stated | PIC (1.00) |
| Germanischer Lloyd AG | DEGermany | Participant | EUR 273,899 | PIC (1.00) |
| Hamburgische Schiffbau-Versuchsanstalt GmbH | DEGermany | Participant | EUR 309,000 | PIC (1.00) |
| MEYER WERFT GmbH | DEGermany | Participant | EUR 49,838 | PIC (1.00) |
| Sofartsstyrelsen | DKDenmark | Participant | EUR 96,005 | known name (0.95) |
| Meyer Turku OY | FIFinland | Participant | EUR 52,460 | PIC (1.00) |
| Chantiers de L'Atlantique | FRFrance | Participant | EUR 52,663 | PIC (1.00) |
| Carnival PLC | GBUnited Kingdom | Participant | EUR 24,320 | PIC (1.00) |
| Lloyd's Register Emea Ips | GBUnited Kingdom | Participant | EUR 75,152 | PIC (1.00) |
| Maritime and Coastguard Agency | GBUnited Kingdom | Participant | EUR 85,450 | known name (0.95) |
| Royal Caribbean Cruise Line | GBUnited Kingdom | Participant | EUR 16,480 | PIC (1.00) |
| Safety at Sea Limited | GBUnited Kingdom | Participant | EUR 209,542 | PIC (1.00) |
| University of Strathclyde | GBUnited Kingdom | Participant | EUR 477,844 | known name (0.95) |
| Fincantieri SpA | ITItaly | Participant | EUR 64,070 | PIC (1.00) |
| Universita Degli Studi di Trieste | ITItaly | Participant | EUR 73,520 | known name (0.95) |
| Color Line Marine As | NONorway | Participant | EUR 39,725 | PIC (1.00) |
| Dnv As | NONorway | Participant | EUR 278,915 | PIC (1.00) |
Changes of the consortium
First seen on with 19 participants from 9 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.