Skip to content

FP7

VANESSA

Validation of Numerical Engineering Simulations: Standardisation Actions

Programme
Seventh Framework Programme
Started
Ends
Duration
18 months
Total cost
EUR 587,892
EU contribution
EUR 491,508
Participants
8 from 5 countries
Topic
FP7_NMP.2012.4.0-2
Grant agreement
319116

Coordinated by The University of Liverpool (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
The University of LiverpoolGBUnited KingdomCoordinatorEUR 110,781PIC (1.00)
Eidgenossische Materialprufungs- und ForschungsanstaltCHSwitzerlandParticipantEUR 104,618PIC (1.00)
Schweizerische Normen-Vereinigung SnvCHSwitzerlandParticipantEUR 57,179PIC (1.00)
Dantec Dynamics GmbHDEGermanyParticipantEUR 52,429PIC (1.00)
High Performance Space Structure Systems GmbHDEGermanyParticipantEUR 39,723PIC (1.00)
National Nuclear Laboratory LimitedGBUnited KingdomParticipantEUR 40,076known name (0.95)
Panepistimio PatronGRGreeceParticipantEUR 45,903PIC (1.00)
Centro Ricerche Fiat ScpaITItalyParticipantEUR 40,799PIC (1.00)

Changes of the consortium

First seen on with 8 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.