Skip to content

FP7

NEUTRONSOURCEESS

The European Spallation Neutron Source (ESS)

Programme
Seventh Framework Programme
Started
Ends
Duration
24 months
Total cost
EUR 6,612,468
EU contribution
EUR 4,999,996
Participants
8 from 8 countries
Topic
FP7_INFRA-2007-2.2-01
Grant agreement
202247

Coordinated by Paul Scherrer Institut (CHSwitzerland).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Paul Scherrer InstitutCHSwitzerlandCoordinatorEUR 978,033known name (0.95)
Forschungszentrum Julich GmbHDEGermanyParticipantEUR 499,824known name (0.97)
Consorcio Para la Construccion, Equipamiento y Explotacion de la Sede Espanola de la Fuente Europea de Neutrones Por EspalacionESSpainParticipantEUR 708,796PIC (1.00)
University of HuddersfieldGBUnited KingdomParticipantEUR 732,127known name (0.95)
Ess Magyarorszag Europai Anyagtudom Anyi Nanotechnilogiai Es Molekulari S Biologiai Kutatokozpont Nonprofit Kft*ess Hungary NcHUHungaryParticipantEUR 584,397PIC (1.00)
Consorzio Nazionale Interuniversitario Per le Scienze Fisiche della MateriaITItalyParticipantEUR 122,849PIC (1.00)
Latvijas UniversitateLVLatviaParticipantEUR 161,039known name (0.95)
Lunds UniversitetSESwedenParticipantEUR 577,339known name (0.95)

Changes of the consortium

First seen on with 8 participants from 8 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.