FP7
CARBONES
30-year re-analysis of CARBON fluxES and pools over Europe and the Globe
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 36 months
- Total cost
- EUR 3,491,018
- EU contribution
- EUR 2,561,699
- Participants
- 14 from 7 countries
- Topic
- FP7_SPA.2009.1.1.02
- Grant agreement
- 242316
Coordinated by Noveltis Sas (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Noveltis Sas | FRFrance | Coordinator | EUR 402,566 | PIC (1.00) |
| Eidgenoessische Technische Hochschule Zuerich | CHSwitzerland | Participant | EUR 117,289 | PIC (1.00) |
| Peking University | CNChina | Participant | EUR 178,800 | PIC (1.00) |
| Max-Planck-Gesellschaft Zur Forderung der Wissenschaften Ev | DEGermany | Participant | EUR 150,000 | known name (0.95) |
| University of Stuttgart | DEGermany | Participant | EUR 173,076 | PIC (1.00) |
| European Forest Institute | FIFinland | Participant | EUR 70,693 | PIC (1.00) |
| Climmod Engineering Sarl | FRFrance | Participant | EUR 199,658 | PIC (1.00) |
| Thales Alenia Space France | FRFrance | Participant | EUR 54,596 | known name (0.95) |
| Aea Technology PLC | GBUnited Kingdom | Participant | EUR 74,616 | PIC (1.00) |
| Cambridge Environmental Research Consultants Ltd | GBUnited Kingdom | Participant | EUR 280,200 | PIC (1.00) |
| Met Office | GBUnited Kingdom | Participant | EUR 217,420 | known name (0.95) |
| Ricardo-Aea Ltd | GBUnited Kingdom | Participant | EUR 28,235 | PIC (1.00) |
| The University Court of the University of Aberdeen | GBUnited Kingdom | Participant | EUR 97,761 | PIC (1.00) |
| Stichting Wageningen Research | NLNetherlands | Participant | EUR 97,468 | known name (0.95) |
Changes of the consortium
First seen on with 14 participants from 7 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.