Skip to content

FP7

REMO

Online Remote Condition Monitoring of Tidal Stream Generators

Programme
Seventh Framework Programme
Started
Ends
Duration
24 months
Total cost
EUR 1,416,974
EU contribution
EUR 1,102,000
Participants
9 from 4 countries
Topic
FP7_SME-2012-1
Grant agreement
314839

Coordinated by Twi Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Twi LimitedGBUnited KingdomCoordinatorEUR 88,855known name (0.95)
Corporate Services InternationalBEBelgiumParticipantEUR 212,743PIC (1.00)
Engitec LimitedCYCyprusParticipantEUR 46,174PIC (1.00)
Wlb LimitedCYCyprusParticipantEUR 167,045PIC (1.00)
Desarrollo y Gestion Industrial y del Medio Ambiente SAESSpainParticipantEUR 174,266PIC (1.00)
Brunel University LondonGBUnited KingdomParticipantEUR 45,073known name (0.95)
Pulse Tidal LimitedGBUnited KingdomParticipantEUR 66,012PIC (1.00)
Stirling Dynamics LtdGBUnited KingdomParticipantEUR 206,502PIC (1.00)
Tangent Technologies LtdGBUnited KingdomParticipantEUR 95,330PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 4 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.