Skip to content

FP7

FUTURAIL

Job Opportunities for the Railway Community of Tomorrow

Programme
Seventh Framework Programme
Started
Ends
Duration
18 months
Total cost
EUR 262,080
EU contribution
EUR 262,080
Participants
5 from 4 countries
Topic
FP7_SST-2007-6.0-03
Grant agreement
218596

Coordinated by Instituto Superior Tecnico (PTPortugal).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Instituto Superior TecnicoPTPortugalCoordinatorEUR 80,849known name (0.95)
Eurnex e. v.DEGermanyParticipantEUR 26,750PIC (1.00)
TSB Innovationsagentur Berlin GmbHDEGermanyParticipantEUR 59,920PIC (1.00)
Union Internationale des Chemins de FerFRFranceParticipantEUR 37,985PIC (1.00)
Consorzio Nazionale Interuniversitario Per i Trasporti e la LogisticaITItalyParticipantEUR 56,576PIC (1.00)

Changes of the consortium

First seen on with 5 participants from 4 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.