H2020
PivotBuoy
PivotBuoy - An Advanced System for Cost-effective and Reliable Mooring, Connection, Installation & Operation of Floating Wind
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 3,960,065
- EU contribution
- EUR 3,960,065
- Participants
- 11 from 6 countries
- Topic
- H2020_LC-SC3-RES-11-2018
- Grant agreement
- 815159
Coordinated by Exponential Renewables SL (ESSpain).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Exponential Renewables SL | ESSpain | Coordinator | EUR 1,412,200 | PIC (1.00) |
| Esm Energie- und Schwingungstechnik Mitsch GmbH | DEGermany | Participant | EUR 107,125 | PIC (1.00) |
| Germanischer Lloyd Industrial Services GmbH | DEGermany | Third party | Not stated | PIC (1.00) |
| Danmarks Tekniske Universitet | DKDenmark | Participant | EUR 204,000 | known name (0.95) |
| Dnv Denmark As | DKDenmark | Third party | Not stated | PIC (1.00) |
| Consorcio Para El Diseno, Construccion, Equipamiento y Explotacion de la Plataforma Oceanica de Canarias | ESSpain | Participant | EUR 303,815 | VAT number (0.97) |
| Desarrollo y Gestion Industrial y del Medio Ambiente SA | ESSpain | Participant | EUR 892,974 | PIC (1.00) |
| Noble Denton Consultants Limited | GBUnited Kingdom | Third party | Not stated | PIC (1.00) |
| Intecsea B.V. | NLNetherlands | Participant | EUR 399,175 | PIC (1.00) |
| Cnet Centre for New Energy Technologies SA | PTPortugal | Participant | EUR 285,000 | PIC (1.00) |
| WAVEC/OFFSHORE Renewables - Centro de Energia Offshore Associacao | PTPortugal | Participant | EUR 224,214 | PIC (1.00) |
Changes of the consortium
First seen on with 11 participants from 6 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.