Skip to content

H2020

PJ06 ToBeFREE

Trajectory based Free Routing

Programme
Horizon 2020
Started
Ends
Duration
38 months
Total cost
EUR 9,722,503
EU contribution
EUR 5,965,008
Participants
27 from 18 countries
Topic
H2020_SESAR.IR-VLD.Wave1-13-2015
Grant agreement
734129

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Austro Control Osterreichische Gesellschaft Fur Zivilluftfahrt MbhATAustriaParticipantEUR 66,500known name (0.95)
Eurocontrol - European Organisation for the Safety of Air NavigationBEBelgiumParticipantEUR 0PIC (1.00)
Darjavno Predpriyatie Rakovodstvo na Vazdushnoto Dvijenie TppBGBulgariaThird partyNot statedPIC (1.00)
Skyguide, SA Suisse Pour les Services de la Navigation Aerienne Civils et MilitairesCHSwitzerlandParticipantEUR 963,200PIC (1.00)
Skysoft-Atm SACHSwitzerlandThird partyNot statedPIC (1.00)
Rizeni Letoveho Provozu Ceske Republiky Statni PodnikCZCzechiaParticipantEUR 0known name (0.95)
Leonardo Germany GmbHDEGermanyThird partyNot statedPIC (1.00)
NaviairDKDenmarkParticipantEUR 133,476known name (0.95)
Centro de Referencia Investigacion Desarrollo e Innovacion Atm, A.I.E.ESSpainThird partyNot statedVAT number (0.97)
EnaireESSpainParticipantEUR 733,669known name (0.95)
Indra Sistemas SAESSpainParticipantEUR 617,907PIC (1.00)
Ingenieria y Economia del Transporte Sme Mp SAESSpainThird partyNot statedPIC (1.00)
Meteo-FranceFRFranceThird partyNot statedknown name (0.95)
Thales Las France SasFRFranceParticipantEUR 444,017PIC (1.00)
Hrvatska Kontrola Zracne Plovidbe DooHRCroatiaParticipantEUR 6,300VAT number (0.97)
Udaras Eitliochta na Heireann the Irish Aviation AuthorityIEIrelandParticipantEUR 0VAT number (0.97)
Consorzio Sicta Sistemi Innovativi Per Il Controllo del Traffico AereoITItalyThird partyNot statedPIC (1.00)
Deep Blue SRLITItalyThird partyNot statedPIC (1.00)
Enav SpAITItalyParticipantEUR 428,505known name (0.95)
Techno Sky SRL Technologies for Air Traffic ManagementITItalyThird partyNot statedPIC (1.00)
Akcine Bendrove Oro NavigacijaLTLithuaniaParticipantEUR 234,019known name (0.95)
Politechnika Rzeszowska Im Ignacego Lukasiewicza PrzPLPolandThird partyNot statedVAT number (0.97)
Polska Agencja Zeglugi PowietrznejPLPolandParticipantEUR 823,384known name (0.97)
Navegacao Aerea de Portugal - Nav Portugal EpePTPortugalThird partyNot statedknown name (0.95)
Kontrola Letenje Srbije i Crne Goresmatsa Doo BeogradRSSerbiaThird partyNot statedPIC (1.00)
LuftfartsverketSESwedenParticipantEUR 70,000known name (0.95)
Letove Prevadzkove Sluzby Slovenskej Republiky, Statny PodnikSKSlovakiaParticipantEUR 0known name (0.95)

Changes of the consortium

First seen on with 27 participants from 18 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.