Skip to content

FP7

SMW

Single Molecule Workstation

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 3,070,119
EU contribution
EUR 2,066,150
Participants
10 from 4 countries
Topic
FP7_NMP-2007-1.2-2
Grant agreement
213717

Coordinated by Till I.D. GmbH (DEGermany).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Till I.D. GmbHDEGermanyCoordinatorEUR 413,600PIC (1.00)
Agilent Technologies Osterreich GmbHATAustriaParticipantEUR 292,698PIC (1.00)
Universitat LinzATAustriaParticipantEUR 366,700PIC (1.00)
Arivis GmbHDEGermanyParticipantEUR 18,000PIC (1.00)
Holoeye Photonics AGDEGermanyParticipantEUR 324,600PIC (1.00)
Multiple Image Tools GmbHDEGermanyParticipantEUR 141,600PIC (1.00)
Till Photonics GmbHDEGermanyParticipantEUR 146,680PIC (1.00)
TILL Photonics GmbHDEGermanyParticipantEUR 31,272PIC (1.00)
Anasys Instruments LimitedGBUnited KingdomParticipantEUR 191,500PIC (1.00)
The Henryk Niewodniczanski Institute of Nuclear Physics, Polish Academy of SciencesPLPolandParticipantEUR 139,500PIC (1.00)

Changes of the consortium

First seen on with 10 participants from 4 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.