FP7

WHATER

Water Harvesting Technologies Revisited: Potentials for Innovations, Improvements and Upscaling in Sub-Saharan Africa

Programme
Seventh Framework Programme
Started
Ends
Duration
54 months
Total cost
EUR 2,456,726
EU contribution
EUR 1,999,930
Participants
8 from 7 countries
Topic
FP7_ENV.2010.3.1.1-4
Grant agreement
266360

Coordinated by Stichting Vu (NLNetherlands).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Stichting VuNLNetherlandsCoordinatorEUR 636,442known name (0.95)
Institut de L'Environnement et de Recherches AgricolesBFBurkina FasoParticipantEUR 115,609PIC (1.00)
Arbaminch University*amuETEthiopiaParticipantEUR 76,125PIC (1.00)
International Centre for Research in Agroforestry (Icraf)KEKenyaParticipantEUR 219,535PIC (1.00)
Vereniging Voor Christelijk Hoger Onderwijs Wetenschappelijk Onderzoek en PatientenzorgNLNetherlandsParticipantNot statedPIC (1.00)
Stockholms UniversitetSESwedenParticipantEUR 285,636known name (0.95)
Sokoine University of AgricultureTZTanzaniaParticipantEUR 128,026PIC (1.00)
University of Kwazulu-NatalZASouth AfricaParticipantEUR 269,640PIC (1.00)

Changes of the consortium

First seen on with 8 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.