Skip to content

FP7

HIPRWIND

High Power, high Reliability offshore wind technology

Programme
Seventh Framework Programme
Started
Ends
Duration
56 months
Total cost
EUR 18,304,626
EU contribution
EUR 11,021,621
Participants
21 from 7 countries
Topic
FP7_ENERGY.2010.2.3-1
Grant agreement
256812

Coordinated by Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev (DEGermany).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung EvDEGermanyCoordinatorEUR 2,294,727known name (0.95)
1-TECH SprlBEBelgiumParticipantEUR 356,157PIC (1.00)
Micromega Dynamics SABEBelgiumParticipantEUR 196,201PIC (1.00)
Universitaet SiegenDEGermanyParticipantEUR 141,033PIC (1.00)
Wolfel Engineering GmbH + Co. KGDEGermanyParticipantEUR 447,942PIC (1.00)
A.L.E. Heavylift Iberica SAESSpainParticipantEUR 555,160PIC (1.00)
Acciona Generacion Renovable, S.A.ESSpainParticipantEUR 193,954known name (0.95)
Acciona Windpower SAESSpainParticipantEUR 109,946PIC (1.00)
Fundacion Tecnalia Research & InnovationESSpainParticipantEUR 391,150PIC (1.00)
Ingenieria y Diseño Europeo S.A.ESSpainParticipantEUR 2,383,814PIC (1.00)
Ingeteam Service SAESSpainParticipantEUR 664,194PIC (1.00)
Qi Energy Assessment SLESSpainParticipantEUR 91,591PIC (1.00)
Vicinay Cadenas Sociedad AnonimaESSpainParticipantEUR 567,485PIC (1.00)
Bureau Veritas SAFRFranceParticipantEUR 83,640PIC (1.00)
Technip Energies FranceFRFranceParticipantEUR 96,738PIC (1.00)
Offshore Renewable Energy CatapultGBUnited KingdomParticipantEUR 55,500known name (0.95)
Twi LimitedGBUnited KingdomParticipantEUR 131,740known name (0.95)
Mammoet Europe BVNLNetherlandsParticipantEUR 8,934PIC (1.00)
Dr Techn Olav Olsen AsNONorwayParticipantEUR 509,481PIC (1.00)
Norges Teknisk-Naturvitenskapelige Universitet NtnuNONorwayParticipantEUR 666,786known name (0.95)
Sintef Energi AsNONorwayParticipantEUR 388,498PIC (1.00)

Changes of the consortium

First seen on with 21 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.