Building Energy Efficiency for Massive market UPtake

Programme
Seventh Framework Programme
Started
Ends
Duration
48 months
Total cost
EUR 7,697,783
EU contribution
EUR 4,858,848
Participants
20 from 7 countries
Topic
FP7_ENERGY-2007-8.1-02
Grant agreement
260039

Coordinated by Acciona Construccion SA (ESSpain).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Acciona Construccion SAESSpainCoordinatorNot statedPIC (1.00)
Eidgenoessische Technische Hochschule ZuerichCHSwitzerlandParticipantNot statedPIC (1.00)
Siemens Schweiz AGCHSwitzerlandParticipantNot statedPIC (1.00)
Basf Construction Solutions GmbHDEGermanyParticipantNot statedPIC (1.00)
Luwoge Consult GmbHDEGermanyParticipantNot statedPIC (1.00)
Bax Innovation Consulting SLESSpainParticipantNot statedPIC (1.00)
Instituto Tecnologico de AragonESSpainParticipantNot statedknown name (0.95)
Mac Puar SAESSpainParticipantNot statedPIC (1.00)
Solintel M & P SLESSpainParticipantNot statedPIC (1.00)
Icf Novedis SAFRFranceParticipantNot statedPIC (1.00)
NobatekFRFranceParticipantNot statedPIC (1.00)
Dura Vermeer Groep NVNLNetherlandsParticipantNot statedPIC (1.00)
Eneco BVNLNetherlandsParticipantNot statedknown name (0.95)
Stichting WoonbronNLNetherlandsParticipantNot statedPIC (1.00)
Technische Universiteit DelftNLNetherlandsParticipantNot statedknown name (0.95)
Universiteit MaastrichtNLNetherlandsParticipantNot statedknown name (0.95)
ISA - Intelligent Sensing Anywhere S.A.PTPortugalParticipantNot statedPIC (1.00)
Alingsashem ABSESwedenParticipantNot statedknown name (0.95)
Rise Research Institutes of Sweden ABSESwedenParticipantNot statedknown name (0.95)
Skanska Sverige ABSESwedenParticipantNot statedPIC (1.00)

Changes of the consortium

First seen on with 20 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.