SHEER

SHale gas Exploration and Exploitation induced Risks

Programme
Horizon 2020
Started
Ends
Duration
36 months
Total cost
EUR 2,680,470
EU contribution
EUR 2,601,720
Participants
9 from 6 countries
Topic
H2020_LCE-16-2014
Grant agreement
640896

Coordinated by Gfz Helmholtz-Zentrum Fur Geoforschung (DEGermany).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Gfz Helmholtz-Zentrum Fur GeoforschungDEGermanyCoordinatorEUR 239,000known name (0.97)
Rskw LtdGBUnited KingdomParticipantEUR 345,313PIC (1.00)
University of GlasgowGBUnited KingdomParticipantEUR 210,000known name (0.95)
University of Keele Royal CharterGBUnited KingdomParticipantEUR 291,808PIC (1.00)
AMRA - Analisi e Monitoraggio del Rischio Ambientale ScarlITItalyParticipantEUR 715,625PIC (1.00)
Universita Degli Studi di Napoli Federico IIITItalyThird partyNot statedknown name (0.95)
Koninklijk Nederlands Meteorologisch Instituut-KnmiNLNetherlandsParticipantEUR 119,975known name (0.95)
Instytut Geofizyki Polskiej Akademii NaukPLPolandParticipantEUR 680,000known name (0.97)
University of WyomingUSUnited StatesParticipantEUR 0PIC (1.00)

Changes of the consortium

First seen on with 9 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.