FP7
AFTER
A Framework for electrical power sysTems vulnerability identification,dEfense and Restoration
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 40 months
- Total cost
- EUR 5,050,292
- EU contribution
- EUR 3,473,803
- Participants
- 14 from 8 countries
- Topic
- FP7_SEC-2010.2.3-2
- Grant agreement
- 261788
Coordinated by Ricerca Sul Sistema Energetico - Rse SpA (ITItaly).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Ricerca Sul Sistema Energetico - Rse SpA | ITItaly | Coordinator | EUR 540,034 | known name (0.95) |
| Elia System Operator | BEBelgium | Participant | EUR 50,957 | known name (0.95) |
| Jrc -Joint Research Centre- European Commission | BEBelgium | Participant | EUR 197,742 | PIC (1.00) |
| Ceps As | CZCzechia | Participant | EUR 94,500 | known name (0.95) |
| Siemens Aktiengesellschaft | DEGermany | Participant | EUR 425,160 | PIC (1.00) |
| Alstom Power Systems | FRFrance | Participant | EUR 79,745 | PIC (1.00) |
| Grid Solutions Sas | FRFrance | Participant | EUR 220,221 | known name (0.95) |
| City University of London | GBUnited Kingdom | Participant | EUR 174,881 | known name (0.95) |
| University College Dublin, National University of Ireland, Dublin | IEIreland | Participant | EUR 381,904 | VAT number (0.97) |
| Agenzia Nazionale Per le Nuove Tecnologie, L'Energia e Lo Sviluppo Economico Sostenibile | ITItaly | Participant | EUR 266,650 | PIC (1.00) |
| Terna - Rete Elettrica Nazionale SpA | ITItaly | Participant | EUR 157,485 | PIC (1.00) |
| Universita Degli Studi di Genova | ITItaly | Participant | EUR 160,780 | known name (0.95) |
| Sintef Energi As | NONorway | Participant | EUR 477,463 | PIC (1.00) |
| Stiftelsen Sintef | NONorway | Participant | EUR 246,281 | PIC (1.00) |
Changes of the consortium
First seen on with 14 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.