Skip to content

FP7

AMAZALERT

Raising the alert about critical feedbacks between climate and long-term land use change in the Amazon

Programme
Seventh Framework Programme
Started
Ends
Duration
39 months
Total cost
EUR 4,757,921
EU contribution
EUR 3,494,420
Participants
15 from 9 countries
Topic
FP7_ENV.2011.1.1.5-1
Grant agreement
282664

Coordinated by Stichting Wageningen Research (NLNetherlands).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
Stichting Wageningen ResearchNLNetherlandsCoordinatorEUR 713,784known name (0.95)
Joanneum Research Forschungsgesellschaft MbhATAustriaParticipantEUR 185,679PIC (1.00)
Universiteit GentBEBelgiumParticipantEUR 156,600known name (0.95)
Fundacion Amigos de la NaturalezaBOBoliviaParticipantEUR 52,330PIC (1.00)
Empresa Brasileira de Pesquisa Agropecuaria EmbrapaBRBrazilParticipantEUR 309,240PIC (1.00)
Instituto Nacional de Pesquisas EspaciaisBRBrazilParticipantEUR 482,270PIC (1.00)
Universidade de Sao PauloBRBrazilParticipantEUR 36,936PIC (1.00)
Universidad Nacional de ColombiaCOColombiaParticipantEUR 41,200PIC (1.00)
Potsdam-Institut Fur Klimafolgenforschung EvDEGermanyParticipantEUR 213,114VAT number (0.97)
Centre National de la Recherche Scientifique CnrsFRFranceParticipantEUR 339,345known name (0.95)
Met OfficeGBUnited KingdomParticipantEUR 319,115known name (0.95)
The University of EdinburghGBUnited KingdomParticipantEUR 228,001known name (0.95)
University of LeedsGBUnited KingdomParticipantEUR 227,998known name (0.95)
Stichting VuNLNetherlandsParticipantEUR 188,808known name (0.95)
Vereniging Voor Christelijk Hoger Onderwijs Wetenschappelijk Onderzoek en PatientenzorgNLNetherlandsParticipantNot statedPIC (1.00)

Changes of the consortium

First seen on with 15 participants from 9 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.