Skip to content

FP7

FISICA

Far Infra-red Space Intereferometer Critical Assessment: Scientific Definition and Technology Development for the Next Generation THz Space Interferometer

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 2,594,403
EU contribution
EUR 1,996,586
Participants
7 from 5 countries
Topic
FP7_SPA.2012.2.2-01
Grant agreement
312818

Coordinated by University College London (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium
OrganisationCountryRoleEU contributionRecognised by
University College LondonGBUnited KingdomCoordinatorEUR 338,054known name (0.95)
University of LethbridgeCACanadaParticipantEUR 302,399PIC (1.00)
Centre National de la Recherche Scientifique CnrsFRFranceParticipantEUR 332,273known name (0.95)
Cardiff UniversityGBUnited KingdomParticipantEUR 349,684known name (0.95)
Glyndwr UNIVERSITY/PRIFYSGOL GlyndwrGBUnited KingdomParticipantEUR 72,057PIC (1.00)
National University of Ireland MaynoothIEIrelandParticipantEUR 161,180known name (0.95)
Assist in Gravitation and Instrumentation (Agi) SRLITItalyParticipantEUR 211,852PIC (1.00)

Changes of the consortium

First seen on with 7 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.