FP7
TEAM_PLAY
Tool Suite for Environmental and Economic Aviation Modelling for Policy Analysis
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 28 months
- Total cost
- EUR 5,265,893
- EU contribution
- EUR 3,867,496
- Participants
- 18 from 8 countries
- Topic
- FP7_AAT.2010.1.3-3.
- Grant agreement
- 266465
Coordinated by Deutsches Zentrum Fur Luft - Und Raumfahrt Ev (DEGermany).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Deutsches Zentrum Fur Luft - Und Raumfahrt Ev | DEGermany | Coordinator | EUR 731,539 | known name (0.97) |
| Ingenieurburo Janicke Gbr | DEGermany | Participant | EUR 69,599 | PIC (1.00) |
| Anotec Consulting SL | ESSpain | Participant | EUR 77,460 | PIC (1.00) |
| Airbus Operations Sas | FRFrance | Participant | EUR 112,114 | PIC (1.00) |
| Ecole Nationale de L Aviation Civile | FRFrance | Participant | EUR 132,300 | known name (0.95) |
| Envisa Sas | FRFrance | Participant | EUR 450,534 | PIC (1.00) |
| Safran Aircraft Engines | FRFrance | Participant | EUR 98,163 | PIC (1.00) |
| Aea Technology PLC | GBUnited Kingdom | Participant | Not stated | PIC (1.00) |
| Cambridge Environmental Research Consultants Ltd | GBUnited Kingdom | Participant | EUR 61,050 | PIC (1.00) |
| Limitedskies Limited | GBUnited Kingdom | Participant | EUR 43,909 | PIC (1.00) |
| Ricardo-Aea Ltd | GBUnited Kingdom | Participant | EUR 86,878 | PIC (1.00) |
| The Chancellor Masters and Scholars of the University of Cambridge | GBUnited Kingdom | Participant | EUR 45,075 | known name (0.95) |
| The Manchester Metropolitan University | GBUnited Kingdom | Participant | EUR 193,125 | PIC (1.00) |
| Stichting Koninklijk Nederlands Lucht - En Ruimtevaartcentrum | NLNetherlands | Participant | EUR 929,000 | PIC (1.00) |
| Taks B.V. | NLNetherlands | Participant | EUR 376,679 | PIC (1.00) |
| Institutul National de Cercetare-Dezvoltare Turbomotoare - Comoti | RORomania | Participant | EUR 29,235 | PIC (1.00) |
| Totalforsvarets Forskningsinstitut | SESweden | Participant | EUR 260,438 | PIC (1.00) |
| National Aviation University | UAUkraine | Participant | EUR 108,900 | PIC (1.00) |
Changes of the consortium
First seen on with 18 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.