FP7
ActionPlanT
ActionPlanT - The European ICT Forum for Factories of the Future
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 24 months
- Total cost
- EUR 2,104,954
- EU contribution
- EUR 1,499,964
- Participants
- 11 from 7 countries
- Topic
- FP7_FoF.ICT.2010.10.1
- Grant agreement
- 258617
Coordinated by Sap Se (DEGermany).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Sap Se | DEGermany | Coordinator | EUR 317,044 | PIC (1.00) |
| Agoria Asbl | BEBelgium | Participant | EUR 90,280 | PIC (1.00) |
| Ecole Polytechnique Federale de Lausanne | CHSwitzerland | Participant | EUR 154,882 | PIC (1.00) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | EUR 152,602 | known name (0.95) |
| Platte Consult GmbH | DEGermany | Participant | EUR 239,188 | PIC (1.00) |
| Fundacion Fatronik. | ESSpain | Participant | EUR 58,141 | PIC (1.00) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 69,723 | PIC (1.00) |
| Dassault Systemes | FRFrance | Participant | EUR 0 | PIC (1.00) |
| Intercim Sas | FRFrance | Participant | EUR 146,592 | PIC (1.00) |
| Panepistimio Patron | GRGreece | Participant | EUR 99,777 | PIC (1.00) |
| Politecnico di Milano | ITItaly | Participant | EUR 171,735 | known name (0.95) |
Changes of the consortium
First seen on with 11 participants from 7 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.