Skip to content

H2020

MoSaiQC

Modular Systems for Advanced Integrated Quantum Clocks

Programme
Horizon 2020
Started
Ends
Duration
54 months
Total cost
EUR 4,138,276
EU contribution
EUR 4,138,276
Participants
10 from 6 countries
Topic
H2020_MSCA-ITN-2019
Grant agreement
860579

Coordinated by Universiteit van Amsterdam (NLNetherlands).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Universiteit van AmsterdamNLNetherlandsCoordinatorEUR 796,860known name (0.95)
Technische Universitaet WienATAustriaParticipantEUR 264,207PIC (1.00)
Universitaet InnsbruckATAustriaParticipantEUR 264,207PIC (1.00)
Toptica Photonics AGDEGermanyParticipantEUR 252,788PIC (1.00)
Kobenhavns UniversitetDKDenmarkParticipantEUR 595,044known name (0.95)
Nkt Photonics A/SDKDenmarkParticipantEUR 297,522PIC (1.00)
British Telecommunications PLCGBUnited KingdomParticipantEUR 303,173PIC (1.00)
Teledyne E2V (UK) LimitedGBUnited KingdomParticipantEUR 0PIC (1.00)
The University of BirminghamGBUnited KingdomParticipantEUR 909,518known name (0.95)
Uniwersytet Mikolaja Kopernika w ToruniuPLPolandParticipantEUR 454,957known name (0.97)

Changes of the consortium

First seen on with 10 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.