FP7
CONTAIN
Container Security Advanced Information Networking
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 42 months
- Total cost
- EUR 15,551,461
- EU contribution
- EUR 10,044,904
- Participants
- 20 from 9 countries
- Topic
- FP7_SEC-2010.3.2-1
- Grant agreement
- 261679
Coordinated by Totalforsvarets Forskningsinstitut (SESweden).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Totalforsvarets Forskningsinstitut | SESweden | Coordinator | EUR 1,814,105 | PIC (1.00) |
| European Organisation for Security | BEBelgium | Participant | EUR 155,700 | PIC (1.00) |
| Jrc -Joint Research Centre- European Commission | BEBelgium | Participant | EUR 571,500 | PIC (1.00) |
| Conceptivity Sarl | CHSwitzerland | Participant | EUR 499,280 | PIC (1.00) |
| Ebos Technologies Limited | CYCyprus | Participant | EUR 573,700 | PIC (1.00) |
| Autoridad Portuaria de Valencia | ESSpain | Participant | Not stated | known name (0.95) |
| Fundacion de la Comunidad Valenciana Para la Investigacion, Promocion y Estudios Comerciales de Valenciaport | ESSpain | Participant | EUR 215,800 | PIC (1.00) |
| Novacom Services SA | FRFrance | Participant | EUR 194,527 | PIC (1.00) |
| MJC2 Limited | GBUnited Kingdom | Participant | EUR 693,300 | PIC (1.00) |
| Thales Research & Technology (UK) Limited | GBUnited Kingdom | Participant | EUR 473,677 | PIC (1.00) |
| Nautical Enterprise Centre Ltd. | IEIreland | Participant | EUR 42,990 | PIC (1.00) |
| Agenzia Delle Dogane e Dei Monopoli | ITItaly | Participant | EUR 179,700 | known name (0.95) |
| Consorzio Ib Innovation | ITItaly | Participant | EUR 855,953 | PIC (1.00) |
| Interporto Bologna SpA | ITItaly | Participant | EUR 97,476 | known name (0.95) |
| Italcontainer SpA | ITItaly | Participant | Not stated | PIC (1.00) |
| Selex Elsag SpA | ITItaly | Participant | Not stated | PIC (1.00) |
| Selex Es SpA | ITItaly | Participant | EUR 559,400 | PIC (1.00) |
| So.ge.mar. Societa Generale Magazzini Raccordati Interporto SpA | ITItaly | Participant | EUR 100,600 | PIC (1.00) |
| Telespazio SpA | ITItaly | Participant | EUR 430,582 | PIC (1.00) |
| Thales Italia SpA | ITItaly | Participant | EUR 302,302 | PIC (1.00) |
Changes of the consortium
First seen on with 20 participants from 9 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.