FP7
RETROKIT
RetroKit - Toolboxes for systemic retrofitting
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 48 months
- Total cost
- EUR 9,969,768
- EU contribution
- EUR 6,600,000
- Participants
- 20 from 11 countries
- Topic
- FP7_EeB.NMP.2012-2
- Grant agreement
- 314229
Coordinated by Rina Consulting SpA (ITItaly).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Rina Consulting SpA | ITItaly | Coordinator | EUR 824,775 | PIC (1.00) |
| Iris-Sw | CHSwitzerland | Participant | EUR 100,440 | PIC (1.00) |
| Abgnova GmbH | DEGermany | Participant | EUR 155,489 | PIC (1.00) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | EUR 897,128 | known name (0.95) |
| Sto AG | DEGermany | Participant | EUR 341,168 | PIC (1.00) |
| Dragados SA | ESSpain | Participant | EUR 603,500 | PIC (1.00) |
| Empresa Municipal de la Vivienda y Suelo de Madrid SA | ESSpain | Participant | EUR 308,520 | known name (0.97) |
| Fundacion Tecnalia Research & Innovation | ESSpain | Participant | EUR 234,980 | PIC (1.00) |
| Kokotas Klimatismos Epe | GRGreece | Participant | EUR 192,800 | PIC (1.00) |
| Proigmenes Erevnitikes & Diahiristikes Efarmoges | GRGreece | Participant | EUR 211,200 | PIC (1.00) |
| Delap & Waller Ecoco Limited | IEIreland | Participant | EUR 114,934 | PIC (1.00) |
| Idp SRL | ITItaly | Participant | EUR 122,760 | PIC (1.00) |
| Dura Vermeer Groep NV | NLNetherlands | Participant | EUR 43,582 | PIC (1.00) |
| Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno | NLNetherlands | Participant | EUR 255,632 | known name (0.95) |
| Segel As | NONorway | Participant | EUR 206,820 | PIC (1.00) |
| Stiftelsen Sintef | NONorway | Participant | EUR 491,806 | PIC (1.00) |
| Bergamo Tecnologie Spzoo | PLPoland | Participant | EUR 443,926 | PIC (1.00) |
| Icpe SA | RORomania | Participant | EUR 219,360 | PIC (1.00) |
| Blatraden AB | SESweden | Participant | EUR 367,568 | PIC (1.00) |
| Rise Research Institutes of Sweden AB | SESweden | Participant | EUR 463,610 | known name (0.95) |
Changes of the consortium
First seen on with 20 participants from 11 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.