FP7
TOISE
Trusted Computing for European Embedded devices
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 35 months
- Total cost
- EUR 245,845,524
- EU contribution
- EUR 3,617,522
- Participants
- 18 from 5 countries
- Topic
- FP7_SP1-JTI-ENIAC-2010-2
- Grant agreement
- 282557
Coordinated by Thales (FRFrance).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Thales | FRFrance | Coordinator | EUR 378,168 | PIC (1.00) |
| Proton World International NV | BEBelgium | Participant | EUR 189,155 | PIC (1.00) |
| Agencia Estatal Consejo Superior de Investigaciones Cientificas | ESSpain | Participant | EUR 63,916 | PIC (1.00) |
| Tecnologias Servicios Telematicos Ysistemas SA | ESSpain | Participant | EUR 89,429 | PIC (1.00) |
| Universidad de Cantabria | ESSpain | Participant | EUR 40,548 | known name (0.95) |
| Airbus Group Sas | FRFrance | Participant | EUR 105,277 | PIC (1.00) |
| Institut Mines-Telecom | FRFrance | Participant | EUR 72,665 | known name (0.95) |
| Magillem Design Services Sas | FRFrance | Participant | EUR 74,470 | PIC (1.00) |
| Secure-Ic Sas | FRFrance | Participant | EUR 192,822 | PIC (1.00) |
| Stmicroelectronics Rousset Sas | FRFrance | Participant | EUR 518,767 | PIC (1.00) |
| Thales Communication & Securite Numeriques SA | FRFrance | Participant | EUR 307,938 | PIC (1.00) |
| Elliniki Aeroporiki Viomichania Anonymi Etaireia | GRGreece | Participant | EUR 83,465 | PIC (1.00) |
| Erevnitiko Panepistimiako Institouto Systimaton Epikoinonion Kai Ypologiston | GRGreece | Participant | EUR 41,750 | PIC (1.00) |
| Azcom Technology SRL | ITItaly | Participant | EUR 97,361 | PIC (1.00) |
| Numonyx Italy Srl | ITItaly | Participant | EUR 269,705 | PIC (1.00) |
| Politecnico di Milano | ITItaly | Participant | EUR 85,212 | known name (0.95) |
| Stmicroelectronics SRL | ITItaly | Participant | EUR 504,206 | PIC (1.00) |
| Universita' Degli Studi di Milano-Bicocca | ITItaly | Participant | EUR 63,126 | known name (0.95) |
Changes of the consortium
First seen on with 18 participants from 5 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.