H2020
EUCP
European Climate Prediction system
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 54 months
- Total cost
- EUR 12,999,515
- EU contribution
- EUR 12,999,515
- Participants
- 18 from 10 countries
- Topic
- H2020_SC5-02-2017
- Grant agreement
- 776613
Coordinated by Met Office (GBUnited Kingdom).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Met Office | GBUnited Kingdom | Coordinator | EUR 1,662,701 | known name (0.95) |
| Internationales Institut Fuer Angewandte Systemanalyse | ATAustria | Participant | EUR 504,964 | PIC (1.00) |
| Eidgenoessische Technische Hochschule Zuerich | CHSwitzerland | Participant | EUR 815,479 | PIC (1.00) |
| Helmholtz-Zentrum Hereon GmbH | DEGermany | Participant | EUR 700,405 | known name (0.97) |
| Danmarks Meteorologiske Institut | DKDenmark | Participant | EUR 305,393 | known name (0.95) |
| Kobenhavns Universitet | DKDenmark | Participant | EUR 338,153 | known name (0.95) |
| Barcelona Supercomputing Center Centro Nacional de Supercomputacion | ESSpain | Participant | EUR 1,026,594 | VAT number (0.97) |
| Centre National de la Recherche Scientifique Cnrs | FRFrance | Participant | EUR 1,784,060 | known name (0.95) |
| Meteo-France | FRFrance | Third party | Not stated | known name (0.95) |
| United Nations Educational Scientific and Cultural Organization | FRFrance | Participant | EUR 530,250 | PIC (1.00) |
| The Chancellor, Masters and Scholars of the University of Oxford | GBUnited Kingdom | Participant | EUR 595,050 | PIC (1.00) |
| The University of Edinburgh | GBUnited Kingdom | Participant | EUR 277,223 | known name (0.95) |
| Fondazione Centro Euro-Mediterraneosui Cambiamenti Climatici | ITItaly | Participant | EUR 1,110,625 | PIC (1.00) |
| Koninklijk Nederlands Meteorologisch Instituut-Knmi | NLNetherlands | Participant | EUR 877,255 | known name (0.95) |
| Stichting Deltares | NLNetherlands | Participant | EUR 962,230 | known name (0.95) |
| Stichting Netherlands Escience Center | NLNetherlands | Participant | EUR 591,135 | PIC (1.00) |
| Surf BV | NLNetherlands | Third party | Not stated | known name (0.95) |
| Sveriges Meteorologiska och Hydrologiska Institut | SESweden | Participant | EUR 918,000 | known name (0.95) |
Changes of the consortium
First seen on with 18 participants from 10 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.