FP7
SUSPLAN
Development of regional and Pan-European guidelines for more efficient integration of renewable energy into future infrastructures
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 38 months
- Total cost
- EUR 4,570,448
- EU contribution
- EUR 3,322,550
- Participants
- 15 from 11 countries
- Topic
- FP7_ENERGY-2007-7.3-05
- Grant agreement
- 218960
Coordinated by Sintef Energi As (NONorway).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Sintef Energi As | NONorway | Coordinator | Not stated | PIC (1.00) |
| Technische Universitaet Wien | ATAustria | Participant | Not stated | PIC (1.00) |
| Verbund Hydro Power GmbH | ATAustria | Participant | Not stated | known name (0.95) |
| Black Sea Regional Energy Centre | BGBulgaria | Participant | Not stated | PIC (1.00) |
| Deutsche Energie-Agentur GmbH | DEGermany | Participant | Not stated | known name (0.97) |
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Participant | Not stated | known name (0.95) |
| Mvv Energie AG | DEGermany | Participant | Not stated | known name (0.97) |
| Universidad Pontificia Comillas | ESSpain | Participant | Not stated | PIC (1.00) |
| Comhairle Nan Eilean Siar | GBUnited Kingdom | Participant | Not stated | known name (0.95) |
| University of the Highlands and Islands | GBUnited Kingdom | Participant | Not stated | known name (0.95) |
| Ricerca Sul Sistema Energetico - Rse SpA | ITItaly | Participant | Not stated | known name (0.95) |
| Nrg Pallas BV | NLNetherlands | Participant | Not stated | known name (0.95) |
| Ec Brec Instytut Energetyki Odnawialnej Sp Zoo | PLPoland | Participant | Not stated | PIC (1.00) |
| Centrul Pentru Promovarea Energiei Curate Si Eficienta in Romania Enero Asociatiei | RORomania | Participant | Not stated | PIC (1.00) |
| Drustvo za Konsalting i Menadzmentstatkraft Western Balkans Doo*company for Consulting and Management Limited | RSSerbia | Participant | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 15 participants from 11 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.