HORIZON
RE-SKIN
Renewable and Environmental-Sustainable Kit for building INtegration
- Programme
- Horizon Europe
- Started
- Ends
- Duration
- 42 months
- Total cost
- EUR 13,162,312
- EU contribution
- EUR 9,615,237
- Participants
- 21 from 10 countries
- Topic
- HORIZON_HORIZON-CL5-2021-D4-02-02
- Grant agreement
- 101079957
Coordinated by Politecnico di Milano (ITItaly).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Politecnico di Milano | ITItaly | Coordinator | EUR 1,340,000 | known name (0.95) |
| Heliotherm Warmepumpentechnik Ges Mbh | ATAustria | Participant | EUR 496,500 | PIC (1.00) |
| Comite Europeen de Coordination de L'Habitat Social Aisbl | BEBelgium | Participant | EUR 230,000 | PIC (1.00) |
| Revolve Planet | BEBelgium | Participant | EUR 536,875 | PIC (1.00) |
| Obshtina Burgas | BGBulgaria | Participant | EUR 296,875 | PIC (1.00) |
| Teknologisk Institut | DKDenmark | Participant | EUR 589,250 | PIC (1.00) |
| Construcciones Garcia Rama SL | ESSpain | Participant | EUR 774,450 | PIC (1.00) |
| Fundacion Ctic Centro Tecnologico Para El Desarrollo en Asturias de Las Tecnologias de la Informacion | ESSpain | Participant | EUR 571,125 | VAT number (0.97) |
| Indresmat SL | ESSpain | Participant | EUR 322,950 | PIC (1.00) |
| Power Smart Control SL | ESSpain | Participant | EUR 530,063 | PIC (1.00) |
| Viviendas del Principado de Asturias SA | ESSpain | Participant | EUR 265,050 | known name (0.95) |
| Ecole Nationale des Travaux Publics de L'Etat | FRFrance | Participant | EUR 425,500 | known name (0.95) |
| Vilogia SA | FRFrance | Participant | EUR 497,100 | known name (0.95) |
| Stille Eko Drustvo S Ogranicenom Odgovornoscu za Trgovinu i Usluge | HRCroatia | Participant | EUR 505,500 | PIC (1.00) |
| Comune di Milano | ITItaly | Participant | EUR 305,000 | known name (0.95) |
| Enel X SRL | ITItaly | Participant | EUR 408,750 | PIC (1.00) |
| Fondazione Politecnico di Milano | ITItaly | Third party | Not stated | PIC (1.00) |
| Zh SRL | ITItaly | Participant | EUR 507,750 | PIC (1.00) |
| Usefulrisk | LULuxembourg | Participant | EUR 366,750 | PIC (1.00) |
| Rinovasol Global Services BV | NLNetherlands | Participant | EUR 244,499 | PIC (1.00) |
| Solartechno Europe BV | NLNetherlands | Participant | EUR 401,250 | PIC (1.00) |
Changes of the consortium
First seen on with 21 participants from 10 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.