FP7
BioBuild
High Performance, Economical and Sustainable Biocomposite Building Materials
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 42 months
- Total cost
- EUR 7,459,426
- EU contribution
- EUR 4,878,496
- Participants
- 17 from 8 countries
- Topic
- FP7_EeB-NMP.2011-1
- Grant agreement
- 285689
Coordinated by Netcomposites Limited (GBUnited Kingdom).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Netcomposites Limited | GBUnited Kingdom | Coordinator | EUR 678,726 | PIC (1.00) |
| Katholieke Universiteit Leuven | BEBelgium | Participant | EUR 511,282 | PIC (1.00) |
| Transfurans Chemicals Bvba | BEBelgium | Participant | EUR 217,440 | PIC (1.00) |
| Arup GmbH | DEGermany | Participant | EUR 372,900 | PIC (1.00) |
| Fiber-Tech Construction GmbH | DEGermany | Participant | EUR 166,500 | PIC (1.00) |
| Leibniz-Institut Fur Verbundwerkstoffe GmbH | DEGermany | Participant | EUR 404,000 | known name (0.95) |
| 3XN As | DKDenmark | Participant | EUR 145,148 | PIC (1.00) |
| Gxn As | DKDenmark | Participant | EUR 180,852 | PIC (1.00) |
| Acciona Construccion SA | ESSpain | Participant | EUR 393,000 | PIC (1.00) |
| Fibreforce Composites Ltd | GBUnited Kingdom | Participant | EUR 179,355 | PIC (1.00) |
| Cimtec Lab SpA | ITItaly | Participant | EUR 100,861 | PIC (1.00) |
| Covestro Resins BV | NLNetherlands | Participant | EUR 18,835 | PIC (1.00) |
| Holland Composites Industrials BV | NLNetherlands | Participant | EUR 22,025 | PIC (1.00) |
| Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno | NLNetherlands | Participant | EUR 293,712 | known name (0.95) |
| Shr BV | NLNetherlands | Participant | EUR 312,800 | PIC (1.00) |
| Amorim Cork Solutions, S.A | PTPortugal | Participant | EUR 223,731 | PIC (1.00) |
| Laboratorio Nacional de Engenharia Civil | PTPortugal | Participant | EUR 657,329 | VAT number (0.97) |
Changes of the consortium
First seen on with 17 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.