H2020

IN2STEMPO

Innovative Solutions in Future Stations, Energy Metering and Power Supply

Programme
Horizon 2020
Started
Ends
Duration
67 months
Total cost
EUR 5,972,727
EU contribution
EUR 5,972,727
Participants
15 from 8 countries
Topic
H2020_S2R-CFM-IP3-01-2017
Grant agreement
777515

Coordinated by Network Rail Infrastructure Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Network Rail Infrastructure LimitedGBUnited KingdomCoordinatorEUR 923,346known name (0.95)
OBB-Infrastruktur AGATAustriaParticipantEUR 98,907known name (0.95)
Deutsche Bahn AGDEGermanyParticipantEUR 311,080known name (0.97)
Siemens AktiengesellschaftDEGermanyParticipantEUR 114,453PIC (1.00)
Siemens Mobility GmbHDEGermanyParticipantEUR 796,567PIC (1.00)
Caf Turnkey & Engineering Sociedad LimitadaESSpainParticipantEUR 413,291PIC (1.00)
Hameen Ammattikorkeakoulu OYFIFinlandThird partyNot statedknown name (0.95)
VaylavirastoFIFinlandParticipantEUR 88,871known name (0.95)
Alstom Transport SAFRFranceParticipantEUR 302,193PIC (1.00)
France-MancheFRFranceParticipantEUR 0PIC (1.00)
RaileniumFRFranceParticipantEUR 482,174PIC (1.00)
Systra SAFRFranceThird partyNot statedknown name (0.95)
Hitachi Rail Sts SpAITItalyParticipantEUR 399,960PIC (1.00)
Infraestruturas de Portugal SAPTPortugalParticipantEUR 88,880known name (0.95)
Ip Patrimonio - Administracao e Gestao Imobiliaria, SAPTPortugalThird partyNot statedknown name (0.95)

Changes of the consortium

First seen on with 15 participants from 8 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.