Large-scale RINA benchmark on FIRE

Programme
Horizon 2020
Started
Ends
Duration
30 months
Total cost
EUR 1,296,870
EU contribution
EUR 1,199,995
Participants
6 from 5 countries
Topic
H2020_ICT-12-2015
Grant agreement
687871

Coordinated by L.M. Ericsson Limited (IEIreland).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
L.M. Ericsson LimitedIEIrelandCoordinatorEUR 310,750PIC (1.00)
Interuniversitair Micro-Electronica CentrumBEBelgiumParticipantEUR 316,125PIC (1.00)
Fundacio Privada I2CAT, Internet i Innovacio Digital a CatalunyaESSpainParticipantEUR 293,250known name (0.97)
Telefonica Innovacion Digital SLESSpainParticipantEUR 84,870PIC (1.00)
Nextworks SRLITItalyParticipantEUR 195,000PIC (1.00)
The Trustees of Boston UniversityUSUnited StatesParticipantEUR 0PIC (1.00)

Changes of the consortium

First seen on with 6 participants from 5 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.