Skip to content

FP7

STELLAR

Selective Tape-Laying for Cost-Effective Manufacturing of Optimised Multi-Material Components

Programme
Seventh Framework Programme
Started
Ends
Duration
36 months
Total cost
EUR 4,007,208
EU contribution
EUR 2,774,266
Participants
10 from 6 countries
Topic
FP7_FoF.NMP.2013-10
Grant agreement
609121

Coordinated by Netcomposites Limited (GBUnited Kingdom).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Netcomposites LimitedGBUnited KingdomCoordinatorEUR 768,365PIC (1.00)
Montanuniversitaet LeobenATAustriaParticipantEUR 299,052PIC (1.00)
Toyota Motor Europe NVBEBelgiumParticipantEUR 69,668PIC (1.00)
Afpt GmbHDEGermanyParticipantEUR 176,295PIC (1.00)
Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung EvDEGermanyParticipantEUR 860,847known name (0.95)
Gubesch Thermoforming GmbHDEGermanyParticipantEUR 188,757PIC (1.00)
Esi GroupFRFranceParticipantEUR 206,811PIC (1.00)
Cgtech LimitedGBUnited KingdomParticipantEUR 110,400PIC (1.00)
Advanced Fibre Placement Technology BVNLNetherlandsParticipantEUR 45,400PIC (1.00)
Airborne Composites Automation BVNLNetherlandsParticipantEUR 48,671PIC (1.00)

Changes of the consortium

First seen on with 10 participants from 6 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.