Started
Ends
Duration
32 months
Total cost
EUR 1,500,563
EU contribution
EUR 1,500,563
Participants
10 from 7 countries
Topic
H2020_S2R-OC-IP5-03-2015
Grant agreement
730863

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
New Opera AisblBEBelgiumParticipantEUR 51,063PIC (1.00)
Union des Industries Ferroviaires Europeennes - UnifeBEBelgiumParticipantEUR 67,500PIC (1.00)
Vyzkumny Ustav Zeleznicni, AsCZCzechiaParticipantEUR 109,500known name (0.95)
Havellandische Eisenbahn AktiengesellschaftDEGermanyParticipantEUR 97,125known name (0.95)
Technische Universitat BerlinDEGermanyParticipantEUR 173,500known name (0.97)
Perpetuum LimitedGBUnited KingdomParticipantEUR 143,750PIC (1.00)
Lucchini Rs SpAITItalyParticipantEUR 86,000PIC (1.00)
Politecnico di MilanoITItalyParticipantEUR 133,125known name (0.95)
Inertia Technology B.V.NLNetherlandsParticipantEUR 112,000PIC (1.00)
Uzina de Vagoane Aiud SARORomaniaParticipantEUR 157,000PIC (1.00)

Changes of the consortium

First seen on with 10 participants from 7 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.

Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.