H2020
STARGATE
SusTainable AiRports, the Green heArT of Europe
- Programme
- Horizon 2020
- Started
- Ends
- Duration
- 60 months
- Total cost
- EUR 33,024,252
- EU contribution
- EUR 24,816,116
- Participants
- 27 from 8 countries
- Topic
- H2020_LC-GD-5-1-2020
- Grant agreement
- 101037053
Coordinated by Brussels Airport Company (BEBelgium).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Brussels Airport Company | BEBelgium | Coordinator | EUR 7,435,496 | known name (0.95) |
| Air Cargo Belgium | BEBelgium | Participant | EUR 2,261,250 | PIC (1.00) |
| Belgisch Laboratorium van Elektriciteitsindustrie | BEBelgium | Participant | EUR 548,331 | PIC (1.00) |
| Brussels Airlines | BEBelgium | Participant | EUR 125,125 | PIC (1.00) |
| Dhl Aviation | BEBelgium | Participant | EUR 1,053,500 | PIC (1.00) |
| Hydrant Refuelling System | BEBelgium | Third party | Not stated | PIC (1.00) |
| Quatra | BEBelgium | Participant | EUR 563,869 | PIC (1.00) |
| Skeyes | BEBelgium | Participant | EUR 192,500 | known name (0.95) |
| Skytanking | BEBelgium | Participant | EUR 2,190,126 | PIC (1.00) |
| Societe Nationale des Chemins de Fer Belges | BEBelgium | Participant | EUR 609,744 | PIC (1.00) |
| TO70 Belgium | BEBelgium | Third party | Not stated | PIC (1.00) |
| Tractebel Engineering S.A. | BEBelgium | Third party | Not stated | known name (0.95) |
| Tui Airlines Belgium NV | BEBelgium | Participant | EUR 63,875 | PIC (1.00) |
| Universiteit Hasselt | BEBelgium | Participant | EUR 1,118,125 | known name (0.95) |
| Vlaams Instituut Voor de Logistiek Vzw | BEBelgium | Participant | EUR 163,750 | PIC (1.00) |
| Vlaams-Brabant | BEBelgium | Participant | EUR 571,175 | PIC (1.00) |
| Vlaamse Instelling Voor Technologisch Onderzoek N.V. | BEBelgium | Participant | EUR 306,061 | PIC (1.00) |
| YPTO | BEBelgium | Third party | Not stated | known name (0.95) |
| Aeroport Toulouse Blagnac SA | FRFrance | Participant | EUR 1,218,875 | known name (0.95) |
| Sopra Steria Group | FRFrance | Participant | EUR 1,262,188 | PIC (1.00) |
| Integrated Environmental Solutions Limited | GBUnited Kingdom | Third party | Not stated | PIC (1.00) |
| Athens International Airport S.A. | GRGreece | Participant | EUR 1,115,188 | known name (0.95) |
| Budapest Airport Budapest Liszt Ferenc Nemzetkozi Repuloter Uzemelteto Zartkoruen Mukodo Reszvenytarsasag | HUHungary | Participant | EUR 1,075,174 | known name (0.95) |
| Ies R&d | IEIreland | Participant | EUR 925,015 | PIC (1.00) |
| Luxmobility S.A.R.L. | LULuxembourg | Participant | EUR 430,500 | PIC (1.00) |
| Erasmus Centre for Urban,port and Transport Economics BV | NLNetherlands | Participant | EUR 776,875 | PIC (1.00) |
| TO70 BV | NLNetherlands | Participant | EUR 809,375 | PIC (1.00) |
Changes of the consortium
First seen on with 27 participants from 8 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.