Skip to content

FP7

PROFICIENT

SME network business model for collective self-organised processes in the construction and retrofit of energy-efficient residential districts

Programme
Seventh Framework Programme
Started
Ends
Duration
48 months
Total cost
EUR 7,283,941
EU contribution
EUR 5,500,000
Participants
17 from 9 countries
Topic
FP7_EeB.NMP.2012-3
Grant agreement
312219

Coordinated by Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek Tno (NLNetherlands).

Consortium

EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.

Members of the consortium, coordinator first
OrganisationCountryRoleEU contributionRecognised by
Nederlandse Organisatie Voor Toegepast Natuurwetenschappelijk Onderzoek TnoNLNetherlandsCoordinatorEUR 1,341,953known name (0.95)
Rdf Ood Ar di EfBGBulgariaParticipantEUR 189,480PIC (1.00)
Irs Servis SroCZCzechiaParticipantEUR 87,648PIC (1.00)
Stu-k AsCZCzechiaParticipantEUR 235,971PIC (1.00)
Lenze-Luig 3-L-PLAN GbrDEGermanyParticipantEUR 334,986PIC (1.00)
Solintel M & P SLESSpainParticipantEUR 185,280PIC (1.00)
Lancaster Cohousing Company LtdGBUnited KingdomParticipantEUR 162,984PIC (1.00)
University of LancasterGBUnited KingdomParticipantEUR 298,253PIC (1.00)
Energosys Energiahatekonysagi Fejlesztesi Es Finanszirozasi Zartkoruenmukodo Reszvenytarsasag*energosysenergy-Efficiency Development FinanHUHungaryParticipantEUR 170,563PIC (1.00)
Varoskutatas (Metropolitan Researchinstitute) KftHUHungaryParticipantEUR 318,252PIC (1.00)
Becquerel Electric SRLITItalyParticipantEUR 240,960PIC (1.00)
Ipostudio Architetti SRLITItalyParticipantEUR 341,760PIC (1.00)
Demo Consultants BVNLNetherlandsParticipantEUR 441,263PIC (1.00)
Gemeente den HaagNLNetherlandsParticipantEUR 118,480known name (0.95)
STICHTING SBRCURnetNLNetherlandsParticipantEUR 333,366PIC (1.00)
Husbanken Region Midt-NorgeNONorwayParticipantEUR 145,752PIC (1.00)
Stiftelsen SintefNONorwayParticipantEUR 553,050PIC (1.00)

Changes of the consortium

First seen on with 17 participants from 9 countries.

A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.

Project page on CORDIS (opens in new tab)

Where this comes from

EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.