FP7
DORIS
Ground Deformations Risk Scenarios: an Advanced Assessment Service
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 36 months
- Total cost
- EUR 4,710,404
- EU contribution
- EUR 3,395,866
- Participants
- 12 from 7 countries
- Topic
- FP7_SPA.2009.1.1.01
- Grant agreement
- 242212
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Gamma Remote Sensing Research and Consulting AG | CHSwitzerland | Participant | EUR 197,500 | PIC (1.00) |
| Pwc Strategy& (Germany)gmbh | DEGermany | Participant | EUR 67,492 | PIC (1.00) |
| Instituto Geológico y Minero de España | ESSpain | Participant | EUR 295,000 | VAT number (0.97) |
| Tre Altamira Slu | ESSpain | Participant | EUR 240,500 | PIC (1.00) |
| Magyar Foldtani Es Geofizikai Intezet | HUHungary | Participant | EUR 145,000 | PIC (1.00) |
| Agenzia Spaziale Italiana | ITItaly | Participant | EUR 105,000 | known name (0.95) |
| Dipartimento della Protezione Civile | ITItaly | Participant | EUR 110,006 | VAT number (0.97) |
| Tecnologie Per le Osservazioni della Terra Ed i Rischi Naturali | ITItaly | Participant | EUR 431,792 | PIC (1.00) |
| Tre Altamira SRL | ITItaly | Participant | EUR 197,500 | PIC (1.00) |
| Universita Degli Studi di Firenze | ITItaly | Participant | EUR 352,500 | known name (0.95) |
| Booz & Company BV | NLNetherlands | Participant | EUR 120,008 | PIC (1.00) |
| Panstwowy Instytut Geologiczny - Panstwowy Instytut Badawczy | PLPoland | Participant | EUR 86,274 | known name (0.97) |
Changes of the consortium
First seen on with 12 participants from 7 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.