FP7
ProEcoWine
Development of a process to generate a novel plant protection product enriched with micronutrients to replace copper in organic viticulture
- Programme
- Seventh Framework Programme
- Started
- Ends
- Duration
- 24 months
- Total cost
- EUR 1,579,150
- EU contribution
- EUR 1,146,000
- Participants
- 11 from 6 countries
- Topic
- FP7_SME-2012-1
- Grant agreement
- 315546
Coordinated by Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev (DEGermany).
Consortium
EU contribution per participant as the open data of CORDIS states it; for a participant with linked third parties it may include their share, and a participant whose amount the data does not hold or cannot make consistent shows Not stated. A participant who left the project is not listed; see the history below.
| Organisation | Country | Role | EU contribution | Recognised by |
|---|---|---|---|---|
| Fraunhofer Gesellschaft Zur Forderung der Angewandten Forschung Ev | DEGermany | Coordinator | EUR 21,365 | known name (0.95) |
| Iau Service - Werner Bannach | DEGermany | Participant | EUR 280,737 | PIC (1.00) |
| Naturland - Verband Fur Okologischen Landbau Ev | DEGermany | Participant | EUR 75,069 | PIC (1.00) |
| Vinedos de Aldeanueva Sociedad Cooperativa | ESSpain | Participant | EUR 102,485 | PIC (1.00) |
| Centre Technologique Nouvelle-Aquitaine Composites & Materiaux Avances | FRFrance | Participant | Not stated | PIC (1.00) |
| Laboratoire Phenobio Sas | FRFrance | Participant | Not stated | PIC (1.00) |
| Les Vignerons de Buzet Societe Cooperative Agricole | FRFrance | Participant | EUR 104,040 | PIC (1.00) |
| Soproni Egyetem | HUHungary | Participant | Not stated | known name (0.95) |
| A4F Alga Fuel SA | PTPortugal | Participant | EUR 179,820 | PIC (1.00) |
| Alfa Laval Corporate AB | SESweden | Participant | EUR 139,495 | PIC (1.00) |
| Name not shown | Not stated | Participant | Not stated | PIC (1.00) |
Changes of the consortium
First seen on with 11 participants from 6 countries.
A snapshot of each project's members is taken once a month; a change is recorded when a snapshot differs from the one before. A project with no change listed has had the same members since it was first observed.
Project page on CORDIS (opens in new tab)
Where this comes from
- CORDIS: EU research projects (Horizon Europe, Horizon 2020, FP7)Last read on . Licence: Commission Decision 2011/833/EU (reuse of Commission documents). Source: CORDIS, European Commission.Participants and amounts as the Commission's CORDIS database states them.
EU contribution is the amount CORDIS's open data pays to the participant. For a participant with linked third parties it may include their share (the CORDIS page prints the net); an amount the data does not hold is left out, not counted as zero. EDF factsheets state none per participant, so EDF projects count as projects but add nothing to the amounts.
Organisation-level facts only: a name, a country, a role, an amount, a year. A participant is recognised by its PIC where the source gives one, otherwise by name; the page says which. How the data is built.